AustinIO > AI Data Center Exemplars > Fermi Project Matador


Fermi America — Project Matador


Fermi America's Project Matador is the most ambitious behind-the-meter campus in the country: a private-grid complex at Amarillo pairing AI data centers with nuclear, gas, solar, and storage toward 11 GW, next to the Pantex nuclear weapons plant. It is the exemplar of the nuclear-anchored model — and the only one selling firm power to multiple tenants rather than serving a single operator.

AttributeDetail
OperatorFermi America (Nasdaq: FRMI); Texas Tech University System partner
Location~12 mi NE of Amarillo, Carson County, TX (Panhandle), adjacent to Pantex
Distance from Austin~500 mi NW
Campus5,800 acres, 18M sq ft of data centers, 99-year lease
Power modelBehind-the-meter private grid (HyperGrid), multi-tenant
Generation11 GW target: ~6 GW gas + 4.4 GW nuclear (4 Westinghouse AP1000) + SMR + solar/storage; up to 17 GW potential
CoolingWater via 2+ mi large-diameter pipeline (installed)
WorkloadAI training + inference; also targets fabs, defense, government
Compute chipTenant-supplied; anchor tenant TensorWave deploys AMD Instinct GPUs
Anchor tenantTensorWave (neocloud) — 15-yr lease, 222 MW phase 1 (to 650+ MW), ~$6.5B, signed Aug 10 2026
Investment$1.5B+ invested to date; IPO'd on Nasdaq/LSE 2026 (FRMI)
Permitting~6 GW of the planned 17 GW permitted; AP1000s in NRC review
TimelineFirst 1 GW targeted year-end 2026; TensorWave phase 1 delivers late Q3/Q4 2027; nuclear later
StatusUnder construction (gas), permitting (nuclear); first anchor tenant signed

Why it exists here

Project Matador sits on a 5,800-acre, 99-year lease from the Texas Tech University System about 12 miles northeast of Amarillo, immediately adjacent to the Department of Energy's Pantex plant — the nation's primary nuclear weapons facility, which employs roughly 4,600 skilled nuclear professionals. That adjacency is the strategy: Fermi is betting that proximity to Pantex gives it a ready nuclear workforce, a security envelope including a no-fly zone, and credibility with the regulators whose approval its reactors need. Co-founded by former Energy Secretary Rick Perry, Fermi took the company public on Nasdaq under the ticker FRMI in 2026.


The power model

Fermi brands its approach "HyperGrid" — a private, behind-the-meter grid built to serve multiple gigawatt-class tenants, each with a customizable mix of dedicated gas, nuclear, and solar. The target is 11 GW: roughly 6 GW of natural gas as the near-term bridge, 4.4 GW of nuclear anchored by four Westinghouse AP1000 reactors, additional small modular reactors, and solar with storage. Fermi has publicly floated expansion toward 17 GW with added land and permits.

This is the multi-tenant variant of behind-the-meter power. Where Meitner and GW Ranch build generation for a single operator, Matador is a merchant private utility: it develops the firm power and leases it, alongside the data center shells, to hyperscalers, fabs, and government tenants that need multi-gigawatt capacity faster than the public grid can deliver it.


The nuclear timeline

The gas is real and moving; the nuclear is the long pole. TCEQ granted a Clean Air Permit for the first 6 GW of gas generation in February 2026, and Fermi filed for an incremental 5 GW gas permit in March 2026 — enough, if approved, to reach the full 11 GW on gas alone, independent of the reactor schedule. On the nuclear side, the four AP1000s are working through Nuclear Regulatory Commission review, with Hyundai E&C and Doosan Enerbility signed as construction and equipment partners. Near-term, Fermi targets three 500,000 sq ft data center buildings and 1 GW of operational power by year-end 2026 — that first gigawatt is gas.


What runs here

Matador is a multi-tenant campus, so its compute is tenant-supplied — but it now has a named anchor. On August 10, 2026, Fermi signed its first binding customer lease with TensorWave, a neocloud provider, chosen after discussions with roughly a dozen prospective customers. The 15-year turnkey lease covers 222 MW in phase one, expandable above 650 MW across three phases, for approximately $6.5 billion in contracted revenue, with first delivery in late Q3 or early Q4 2027.

TensorWave deploys AMD Instinct GPUs exclusively, so Matador's first workloads are AMD-based AI training and inference sold as cloud capacity — the neocloud pattern that also defines Beacon Point and IREN, where the tenant is a compute reseller rather than a lab or hyperscaler. Fermi has said it expects the lease to be guaranteed by "one of the global leaders in AI." That guarantor is unnamed; market speculation centers on AMD, whose venture arm is a TensorWave investor, but Fermi has not confirmed it. What runs here beyond TensorWave stays open — the campus is designed for many tenants, and only the first is signed.


Suppliers and Co-Located Infrastructure

Supplier Proximity
ABB Switchgear Production International
AMD Instinct MI300X/MI325X Production Domestic
Arista Networks Switch Production Domestic
Caterpillar Generator Production Domestic
City of Amarillo Water Supply Agreement Adjacent
Coherent Optical Transceiver Production Domestic
CoolIT Systems Direct-to-Chip Cooling International
Cummins Power Generation Domestic
Doosan Enerbility Reactor Pressure Vessels International
Doosan Enerbility Steam Generator Production International
Eaton Power Distribution International
Energy Transfer Firm Gas Supply + Pipeline Interconnect Adjacent
Foxconn AI Server Production International
Hitachi Energy Transformer Operations International
Industrial Water Supply (Carson County / Ogallala) Regional
Keystone National Group HV Equipment Facility Domestic
Micron HBM Production Domestic
NVIDIA H100/H200/B200 Production (TSMC) International
NVIDIA Spectrum-X / InfiniBand Production Domestic
On-Site Battery Energy Storage Onsite
On-Site Solar PV Installation Onsite
On-Site Wind Generation Onsite
ONEOK Pipeline Operations Domestic
Permian Basin Natural Gas Pipeline Network Texas
Primoris Energy Services - Phase One Balance of Plant Texas
Quanta Cloud Technology AI Server Production International
Samsung HBM Production International
Schneider Electric Datacenter Solutions Domestic
Siemens Energy Control Systems International
Siemens Energy Generator Production International
Siemens Energy SGT-800 Gas Turbines (Phase One) International
Siemens Energy SGT6-5000F Gas Turbines (Phase Two) Domestic
Siemens Energy Steam Turbine Production International
SK Hynix HBM Production International
SPX Cooling Tower Production Domestic
Supermicro AI Server Manufacturing Domestic
Targa Resources Gas Processing Texas
Titan Production Equipment Fuel Gas Letdown Stations Texas
Trane Chiller Production Domestic
Vertiv Liquid Cooling Production Domestic
Westinghouse AP1000 Reactor Production Domestic
Westinghouse Nuclear Fuel Production Domestic
Wiwynn AI Server Manufacturing International
Xcel Energy / Southwestern Public Service Grid Service Adjacent

Where it fits

Matador is the nuclear-anchored exemplar and the most ambitious of the set. Where GW Ranch and Pecos anchor on gas and Meitner on renewables, Matador is the only Texas campus building gigawatt-scale nuclear into the mix, and the only one structured as a merchant private grid serving many tenants across AI, semiconductors, and defense. It is the fullest expression of the buildout's core move — if the grid cannot deliver the power, build your own, at the scale of a national utility.


Capacity is target/permitted generation, not operational or IT load; nuclear is in NRC review. First anchor tenant (TensorWave, 222 MW phase 1) signed Aug 2026; lease guarantor unnamed. First 1 GW (gas) targeted year-end 2026. Status: gas under construction, nuclear permitting.


Constraints and Considerations

Schedule risk is the most material constraint on Project Matador's announced trajectory. AP1000 deployment timelines have historically slipped at every US installation; first reactor grid-synchronization in 2031-2032 assumes an aggressive permitting and construction schedule that has not been demonstrated at greenfield US sites. If the nuclear timeline slips by 2-4 years, the campus continues operating on gas-and-solar with delayed nuclear baseload, but the strategic premise of nuclear-and-datacenter coupled architecture loses some of its differentiating force. The earlier milestones (Phase 1 commissioning late 2026, datacenter first occupancy 2026-2027, first AP1000 first concrete pour 2027-2028) are the leading indicators that validate or rebase the trajectory.


Related: Behind-the-Meter Power · Water & Cooling · ERCOT Large Load Interconnection · Brownfield Inheritance · AI Data Center Exemplars