Overview
Two Campuses Under One Name
Read the stack from the ground up: land, builder, compute, tenant, program.
Stargate Abilene is the flagship of OpenAI's Stargate program and the first Texas AI campus with substantial live capacity. The name covers two adjacent campuses on Lancium's land in Taylor County. Campus 1, this page, is the Stargate joint venture: Lancium owns the land and power campus, Crusoe built the eight buildings, Oracle owns the GPUs and sells them as Oracle Cloud Infrastructure, and OpenAI is the tenant. Campus 2, next door, is a separate Crusoe build for Microsoft.
They split in March 2026, when OpenAI and Oracle cancelled a planned 600 MW expansion of Campus 1; OpenAI did not want to mix Blackwell and the coming Vera Rubin generation on one site. Microsoft took the adjacent build instead, which is why both "OpenAI's Abilene" and "Microsoft's Abilene" are correct.
| Layer | Campus 1: Stargate | Campus 2: Microsoft |
|---|---|---|
| Program | Stargate joint venture: OpenAI, Oracle, SoftBank, MGX | None: a standalone Microsoft deal |
| Tenant | OpenAI | Microsoft |
| Compute owner and operator | Oracle, as Oracle Cloud Infrastructure | Crusoe, as a merchant AI factory |
| Developer and builder | Crusoe | |
| Chips | Nvidia GB200 NVL72, about 450,000 GPUs planned | |
| Land and power | Lancium Clean Campus: land, substation and on-site gas | |
| Capacity | 1.2 GW in eight buildings; expansion beyond cancelled March 2026 | About 900 MW in two buildings |
| Status | Four of eight buildings live; the rest due through 2026 | Under construction since March 2026 |
Live capacity
Four of Eight Buildings Live
The first two buildings, about 980,000 sq ft and more than 200 MW, went from groundbreaking to operation in about a year; Oracle took its first capacity in September 2025. Four of the eight are now live, with the rest due through 2026. Each building runs up to 100,000 GPUs on one network fabric.
Financing was layered too: $9.6B of JPMorgan debt, $5B of Crusoe and Blue Owl equity, and a $7.1B Newmark construction loan for the second phase.
Abilene is now a cluster. With Vantage's Frontier campus in Shackelford County, also for OpenAI and Oracle, the area holds about 3.5 GW across three campuses.
The supplier ring
The Abilene Supplier Ring
Each supplier placed by distance from the campus and what it supplies.
- United States
- Korea
- Taiwan, Canada and multiple
Select a supplier
Each dot is a supplier. Distance from the center is how close it sits to the campus; the wedge is what it supplies; color is the parent company's home country; a hollow dot is a category the industry supplies but no Abilene source names.
The ring maps 31 suppliers; 18 are confirmed for Abilene and the rest are categories the industry supplies but no Abilene source names, such as the HBM makers and server ODMs. The on-site power wedge is the distinctive one: a 360.5 MW simple-cycle gas plant split between GE Vernova LM2500XPRESS aeroderivatives and Solar Turbines units, chosen because combined-cycle lead times had stretched toward seven years, with Parker Hannifin inlet systems on all 29 turbines.
Crusoe cut the industry's switchgear queue by making its own after buying Easter-Owens Electric in 2022, and Rosendin's Modular Power Solutions delivered about 60% of the electrical systems prefabricated. Grid power from AEP Texas supplements the gas and carries West Texas wind.
All 31 suppliers as a table
| Supplier | Location | Serves | Proximity | Origin | Evidence | Also supplies |
|---|---|---|---|---|---|---|
| Abilene 200MW 138kV Project Substation | Abilene, Texas | Land, grid and transmission | On the campus | United States | Confirmed | - |
| AEP Texas Transmission Interconnection | Corpus Christi, Texas | Land, grid and transmission | Abilene and West Texas | United States | Confirmed | SpaceX Starbase, Tesla Lithium Refinery |
| Closed-Loop / Zero-Evaporation Cooling Design | Abilene, Texas | Data center build | On the campus | United States | Confirmed | - |
| Crusoe In-House Switchgear Manufacturing | Englewood, Colorado | Data center build | Elsewhere in the US | United States | Confirmed | - |
| Digital Building Components - Prefabrication | Phoenix, Arizona | Data center build | Elsewhere in the US | United States | Confirmed | - |
| Direct-to-Chip Liquid Cooling System | Abilene, Texas | Data center build | On the campus | United States | Confirmed | - |
| ERCOT Interconnection | Austin, Texas | Land, grid and transmission | Elsewhere in Texas | United States | Confirmed | - |
| GE Vernova LM2500XPRESS Aeroderivative Fleet | Houston, Texas | On-site power | On the campus | United States | Confirmed | Meta Temple |
| Lancium Clean Campus | Houston, Texas | Land, grid and transmission | On the campus | United States | Confirmed | - |
| Micron HBM Supply | Boise, Idaho | Compute | Elsewhere in the US | United States | Not named for Abilene | Fermi America, Meta Temple |
| Modular Power Solutions - Prefabricated Electrical | McKinney, Texas | Data center build | Elsewhere in Texas | United States | Confirmed | - |
| Mortenson - Electrical Infrastructure EPC | Minneapolis, Minnesota | Land, grid and transmission | Elsewhere in the US | United States | Confirmed | - |
| Natural Gas Supply - West Texas Associated Gas | Abilene, Texas | On-site power | Abilene and West Texas | United States | Not named for Abilene | - |
| Network Switch Supply | Santa Clara, California | Compute | Elsewhere in the US | United States | Not named for Abilene | - |
| NVIDIA GB200 NVL72 Racks | Santa Clara, California | Compute | Elsewhere in the US | United States | Confirmed | Fermi America, Meta Temple |
| On-Site Simple-Cycle Gas Plant (360.5 MW) | Abilene, Texas | On-site power | On the campus | United States | Confirmed | - |
| OpenAI - End Tenant | San Francisco, California | Customer and tenant | Elsewhere in the US | United States | Confirmed | - |
| Optical Transceiver Supply | Saxonburg, Pennsylvania | Compute | Elsewhere in the US | United States | Not named for Abilene | Fermi America, Meta Temple, Tesla Giga Texas |
| Oracle Cloud Infrastructure - Primary Customer | Austin, Texas | Customer and tenant | Elsewhere in Texas | United States | Confirmed | - |
| Parker Hannifin Turbine Inlet Systems | Cleveland, Ohio | On-site power | On the campus | United States | Confirmed | SpaceX Starbase |
| ProEnergy Aero DT35 Units | Sedalia, Missouri | On-site power | On the campus | United States | Not named for Abilene | - |
| Rosendin Electric - Prime Electrical | San Jose, California | Data center build | Elsewhere in the US | United States | Confirmed | Meta Temple |
| Samsung HBM Supply | Hwaseong, South Korea | Compute | Outside the US | Korea | Not named for Abilene | Fermi America, Meta Temple, Tesla Giga Texas |
| Server ODM Rack Integration | Taipei, Taiwan | Compute | Outside the US | Taiwan, Canada and multiple | Not named for Abilene | - |
| SK Hynix HBM Supply | Icheon, South Korea | Compute | Outside the US | Korea | Not named for Abilene | Fermi America, Meta Temple, Tesla Giga Texas |
| Solar Turbines Gas Turbine Supply | San Diego, California | On-site power | On the campus | United States | Not named for Abilene | - |
| Switchgear and UPS OEM Layer | Multiple | Data center build | Outside the US | Taiwan, Canada and multiple | Not named for Abilene | SpaceX Bastrop, Tesla Megapack Brookshire, Fermi America, Meta Temple, Samsung Taylor, SpaceX Starbase, Tesla Giga Texas, Tesla Lithium Refinery |
| Thermal Management Equipment | Westerville, Ohio | Data center build | Elsewhere in the US | United States | Not named for Abilene | Tesla Megapack Brookshire, Fermi America, Meta Temple, Tesla Giga Texas |
| Transformer Supply | Multiple | Data center build | Outside the US | Taiwan, Canada and multiple | Not named for Abilene | - |
| TSMC Blackwell Fabrication | Hsinchu, Taiwan | Compute | Outside the US | Taiwan, Canada and multiple | Not named for Abilene | Fermi America, Meta Temple, Tesla Giga Texas |
| West Texas Wind Generation | Abilene, Texas | On-site power | Abilene and West Texas | United States | Confirmed | - |
Record
Dataset Record
- Dataset
- Stargate Abilene supplier ring (stargate), 31 suppliers; campus figures from the Texas data centers dataset
- Evidence
- Confirmed for Abilene solid; industry categories not named for Abilene hollow
- Origin
- Home country of the parent company
- Also supplies
- Operator matched against the other anchor rings in the Supplier Rings workbook
- Last verified
- Q4 2026