Texas BESS Concentration

ENGIE, Jupiter, Plus Power, Tesla and others · ERCOT · Brazoria, Bexar, Reeves and more

ERCOT's battery energy storage system (BESS) fleet reached 16.5 GW and 28.8 GWh at the end of June 2026, the largest in the US. Growth is slowing: Modo Energy expects about 6 GW of additions in 2026, roughly matching 2025, after near-doubling every year through 2024.

Under 8 GW entering 2025Start of 20257.8 GW 13.9 GW / 22.9 GWh after a record 6 GW yearEnd of 202513.9 GW 14.96 GW / 24.6 GWhEnd of Q1 202615 GW 16.5 GW / 28.8 GWhEnd of Q2 202616.5 GW
Operational
16.5 GW
Energy
28.8 GWh
Added 2025
6 GW
Largest owner
ENGIE
Discharge record
11.98 GW
Sector
Energy

Overview

ERCOT Runs the Largest Battery Fleet in the US

ERCOT (the Electric Reliability Council of Texas) added about 6 GW and 11 GWh of batteries at 60 new sites in 2025, its largest year, ending at 13.9 GW. By the end of June 2026 the fleet stood at 16.5 GW and 28.8 GWh. On July 22, 2026 batteries discharged a record 11,980 MW during a record peak-demand day.

Batteries earn from ERCOT's energy-only market and ancillary services, so merchant projects do not need a utility contract. Real-Time Co-optimization plus Batteries (RTC+B), launched Dec 5, 2025, now co-optimizes battery energy and reserves in real time.

Profile
Operational (June 2026)16.5 GW / 28.8 GWh
2025 additionsAbout 6 GW at 60 sites
2026 forecast5.5 to 6 GW
Largest ownerENGIE, 2.8 GW at end of 2025
Market shareTop five owners hold 47%
Average durationAbout 1.65 hours entering 2026
Discharge record11,980 MW, July 22, 2026
Market changeRTC+B live Dec 5, 2025

Operators

ENGIE Leads a Market Where No Owner Holds a Majority

ENGIE, which bought Broad Reach Power in 2023, held 2.8 GW at the end of 2025, about 20% of the fleet. The top five owners held 47% and the top 10 held 63%.

Selected ERCOT battery owners and projects
OwnerNotable projectsPosition
ENGIEPortfolio across the Texas Triangle and Gulf CoastLargest owner, 2.8 GW
Jupiter PowerCallisto I (200 MW / 400 MWh), central HoustonHouston load-zone specialist
Plus PowerRodeo Ranch (300 MW / 600 MWh), Reeves County, online Dec 2023Standalone storage in West Texas
Greenflash InfrastructureSoho (400 MW / 800 MWh), Brazoria County, online July 2026Safe-harbored over 10 GWh for data center supply
EolianPadua 2 (150 MW / 600 MWh) and Ferdinand (200 MW / 800 MWh), Bexar CountySan Antonio's first four-hour systems
TeslaGambit Angleton (100 MW), Brazoria CountyMegapack maker, deployer and retail power provider

Geography

North and South Load Zones Hold the Most Capacity, Brazoria Led 2025 Additions

Brazoria County south of Houston drew 16% of 2025 additions, nearly 1 GW across eight sites, on available land and strong interconnection near Gulf Coast load. Bexar County gained its first four-hour batteries in Q2 2026. West Texas batteries in Reeves, Pecos and nearby counties firm wind and solar and serve oil-field and data center load.

Operational BESS by ERCOT load zone, end of June 2026
Load zoneCapacity
North4.9 GW
South4.6 GW
West4.0 GW
Houston2.9 GW

Supply Chain

Brookshire Builds Megapacks in Texas While Cells Still Come Largely From China

Tesla began Megapack 3 production at its Brookshire factory in Waller County in August 2026, with 50 GWh of annual capacity. Each Megapack 3 holds about 5 MWh; four form a 20 MWh Megablock. See Tesla Megapack at Brookshire.

Most of the Texas fleet runs on lithium iron phosphate (LFP) cells from Chinese makers such as CATL, BYD and EVE Energy. The 2025 One Big Beautiful Bill Act kept the storage investment tax credit but added prohibited-foreign-entity rules: projects starting construction in 2026 must source at least 55% of material costs outside covered Chinese entities, rising to 75% after 2029. CATL is on the Pentagon's Chinese military companies list.

Constraints

Low Revenues and Queue Withdrawals Are Slowing New Batteries

Battery revenues paced at about $29 per kW-year in early 2026. New queue entries fell to about 14 GW per half-year from a 31 GW peak in the first half of 2025, and a record 13.7 GW withdrew in the first half of 2026. Median time from queue entry to operation rose from 2.3 years for 2021 projects to 4.4 years in 2026.

Nearly all Q2 2026 additions were two hours or longer, as two-hour systems out-earned one-hour systems every month for two years. SB 6 (2025) also has the PUCT (Public Utility Commission of Texas) revisiting transmission cost allocation, which could change battery economics.

Record

Dataset Record

Sources
Modo Energy (2025 annual and Q2 2026 buildout reports), Grid Status, Cleanview, Energy-Storage.news, ESS News, Deutsche Bank, SMM News, Foley Hoag, Power Engineering, ERCOT
Last verified
October 2026