ERCOT Energy Sovereignty

ERCOT · Austin and Taylor · Texas Interconnection

The Electric Reliability Council of Texas (ERCOT) keeps the Texas Interconnection unsynchronized with the rest of the US so that power sold inside it stays outside federal rate regulation. The trade-off is a grid that can import only about 1,220 MW through its DC ties while its peak demand reached 91.1 GW in 2026.

1935Federal Power Act covers interstate powersales 1970Texas Interconnected System becomes ERCOT May 4, 1976Midnight Connection to Oklahoma tests FERCreach 1996ERCOT becomes an independent system operator 2002Retail electric competition opens Feb 2021Winter Storm Uri; 246 deaths in Texas Jun 21, 2025SB 6 sets large-load rules Jul 2026Record peak demand of 91.1 GW
Share of load
About 90%
Customers
27 million
Peak
91.1 GW
Tie imports
About 1,220 MW
Regulator
PUCT
Sector
Energy

Overview

ERCOT Runs a Separate Grid for About 90 Percent of Texas Load

ERCOT schedules power for more than 27 million customers over more than 55,000 miles of transmission lines and more than 1,460 generating units. It owns no plants or wires; it runs the real-time and day-ahead markets, plans transmission and handles generation and large-load interconnection. The Texas Panhandle, El Paso and parts of East Texas sit on the Eastern or Western Interconnection instead; see Texas Panhandle Nexus and Texas Trans-Pecos Nexus.

ERCOT is a membership-based 501(c)(4) nonprofit overseen by the Public Utility Commission of Texas (PUCT) and the Texas Legislature. It lists its headquarters in Austin and runs a control center in Taylor in Williamson County.

Profile
OperatorElectric Reliability Council of Texas
Legal formMembership-based 501(c)(4) nonprofit
OversightPUCT and Texas Legislature
OfficesAustin; control center in Taylor
CustomersMore than 27 million
TransmissionMore than 55,000 miles
Generating unitsMore than 1,460
Record peak91.1 GW, summer 2026
Interconnection headJeff Billo, Vice President, Interconnection and Grid Analysis

Federal reach

Staying Unsynchronized Keeps ERCOT Outside FERC Rate Regulation

The Federal Power Act of 1935 gives the Federal Energy Regulatory Commission (FERC) authority over interstate wholesale power sales and transmission. Because the Texas Interconnection does not run synchronously with neighboring grids, sales inside it count as intrastate and fall to the PUCT. In 1976 Central and South West briefly sent power into Oklahoma to force federal jurisdiction; the legal fight ended in a compromise that allowed limited asynchronous ties.

FERC still reaches ERCOT through reliability. North American Electric Reliability Corporation (NERC) standards apply in Texas and are enforced by the Texas Reliability Entity. Southern Spirit Transmission, Pattern Energy's planned 3,000 MW high-voltage direct current (HVDC) line to Mississippi, is built as an asynchronous tie so that it adds import capacity without changing ERCOT's jurisdiction.

DC ties

Five Small Ties Connect ERCOT to Oklahoma and Mexico

ERCOT puts total import capability at about 1,220 MW: 820 MW from the Southwest Power Pool (SPP) and roughly 400 MW from Mexico's grid, run by CENACE and the Comisión Federal de Electricidad (CFE). During Winter Storm Uri, Mexico cut exports to Texas after Texas restricted gas exports to Mexico.

ERCOT asynchronous ties
TieNeighborCapacityLocation
East DC tieSPP600 MWMonticello, Titus County
North DC tieSPP220 MWOklaunion, Wilbarger County
Railroad DC tieCFE MexicoLargest Mexico tieSharyland, near McAllen
Laredo variable frequency transformerCFE Mexico100 MWLaredo
Eagle Pass DC tieCFE Mexico36 MWEagle Pass

After Uri

Winter Storm Uri Drove Weatherization Rules and the Battery Buildout

Winter Storm Uri in February 2021 froze gas wellheads, pipelines and plant equipment while demand hit winter records. ERCOT ordered rolling outages for days, and the Texas Department of State Health Services counted 246 deaths. Senate Bill 3 (2021) required weatherization of power plants and gas facilities.

ERCOT expanded its ancillary services, adding the ERCOT Contingency Reserve Service for fast-responding resources, and batteries grew to compete in them: about 14.7 GW were added between summer 2025 and summer 2026, bringing the fleet to about 18.9 GW. See Texas BESS Concentration.

AI load

Data Centers Make Up About 90 Percent of New Large-Load Requests

Large-load requests reached about 474 GW by August 2026, about 90 percent of them data centers. ERCOT's preliminary April 2026 forecast put 2032 demand near 368 GW, a figure ERCOT CEO Pablo Vegas said is higher than the load growth ERCOT expects. Senate Bill 6 (SB 6), signed June 21, 2025, set the rules for loads of 75 MW or more, including curtailment in emergencies and disclosure of on-site backup generation.

Jeff Billo, ERCOT's Vice President of Interconnection and Grid Analysis, leads the Batch Zero study. Governor Greg Abbott's Aug 3, 2026 audit order paused that study; ERCOT's verification report is due by Dec 10, 2026. Details are in ERCOT Large Load Interconnection and Texas Data Center Moratorium.

Record

Dataset Record

Sources
ERCOT (company profile, DC tie flows during Winter Storm Uri, Batch Zero board update Sept 2026), Public Utility Commission of Texas, Texas Department of State Health Services, Texas Legislature (SB 3, SB 6), US Energy Information Administration, Bloomberg Government, Rigzone, Energy Ogre, Troutman Pepper Locke, McGuireWoods