Overview
A Powered-Land Park, Not a Data Center
Tract sells the platform; the operators who lease pads bring the buildings, chips and tenants.
Tract Caldwell Valley Technology Park is about 3,000 contiguous acres (2,973) on FM 2720 near Uhland in Caldwell County, roughly 30 miles south of Austin at the midpoint to San Antonio. Tract zones, entitles, powers and connects the land, then leases shovel-ready pads to operators who build the data centers. At up to 4 GW it is one of the largest master-planned data center parks in the US and the anchor of the I-35 South Data Center Corridor.
Tract is a Colorado company founded by former Cologix CEO Grant van Rooyen; the park is held through Fleet DC, created by Tract Capital. It closed the first 1,515 acres from Walton Global Holdings in May 2025 after 18 months of entitlement work, planning more than 2 GW, then added 1,458 contiguous acres in two January 2026 purchases and raised the plan to 4 GW. It asked for no tax abatement.
| Layer | Tract | Pad operator |
|---|---|---|
| Land | Buys large parcels; about 3,000 contiguous acres here | Lease a pad |
| Zoning and entitlement | Wins approvals; 18 months of entitlement work before the first close | Build to the entitled plan |
| Power | Contracts the substation with Bluebonnet and LCRA; gas pipeline on site | Draw grid power or build on-site generation |
| Fiber | Long-haul routes to the site | Connect |
| Buildings, chips and tenants | None | Everything above the pad |
Power
250 MW in 2028, 4 GW at Full Build
Tract signed a Facility Design Agreement with Bluebonnet Electric Cooperative and the Lower Colorado River Authority (LCRA) for a substation scaling to 1.6 GW, with the first 250 MW contracted for the first quarter of 2028. Site preparation is under way and building construction is expected in 2027; the full plan runs past 2030.
The confluence
Transmission, Gas and Fiber on One Parcel
Hover a utility to find it on the site plan.
| Utility | What is there | What it gives a tenant |
|---|---|---|
| Transmission | High-voltage lines and a Bluebonnet Electric Cooperative and LCRA substation scaling to 1.6 GW | Grid power from 2028 |
| Natural gas | Kinder Morgan's Permian Highway pipeline crosses the site | On-site generation for peak and backup without waiting on the ERCOT queue |
| Fiber | Long-haul routes along I-35 between Austin and San Antonio | Low-latency links to both metros' interconnection points |
The gas line is the strategic piece: pad operators can build on-site generation for peak and backup power instead of waiting years in ERCOT's large-load queue. Micron looked at the site for a chip fab before choosing New York, a sign the land and utilities meet semiconductor standards, not only data center ones.
First tenant
PowerHouse Takes 500 Acres
The first disclosed pad operator is PowerHouse Data Centers, owned by American Real Estate Partners (AREP), on about 500 acres inside the park: a reported 700 MW with an on-site gas plant, for a single large tenant it has not named. PowerHouse's national pipeline is reported above 8 GW.
In April 2026 the PowerHouse land was de-annexed from the City of Uhland into Caldwell County jurisdiction, a route around city opposition seen elsewhere on the corridor.
Neighbors
The Rest of the Corridor
| Campus | Where | Scale |
|---|---|---|
| Prime Data Centers Project Snow | Across FM 2720 | 206 acres; $1.3B first phase, $4.2B in nine buildings |
| Edged Energy | Near Maxwell, on a Waterstone Land Partners parcel | $7.3B, 330 acres; waterless cooling; Phase 1 from June 2026 |
| CloudBurst Evolve San Marcos | Hays and Guadalupe counties | 1.2 GW on its own gas; first 50 MW due late 2026 |
| Sabey San Marcos | Hays County | 786 acres; city negotiation opened June 2025 |
These are separate developments on separate parcels, not part of the Tract park. Together they make the I-35 stretch between Austin and San Antonio the Austin Supercluster's youngest and fastest-forming data center supernode.
Record
Dataset Record
- Sources
- Tract and Caldwell County announcements; Data Center Dynamics, Baxtel and local reporting through October 2026
- Site plan
- Schematic, not to scale; pad layout illustrative
- Last verified
- Q4 2026