CloudBurst Evolve San Marcos

CloudBurst Data Centers and Evolve Holdings · San Marcos Data Center I

A 1.2 GW AI campus in Guadalupe County, between Austin and San Antonio, that runs entirely on gas from the Oasis pipeline. Its gas contract can make more power than the campus plans to use.

First 50 MW, construction from November 2025First phase, Q4 202650 MW Three phases of 400 MWEach of three phases400 MW Up to 1.2 GW in 10-12 buildingsPlanned campus1,200 MW Oasis pipeline gas: more than 1.8 GW of generation potentialGas supply potential1,800 MW
Planned
1.2 GW
Gas potential
1.8 GW+
First phase
50 MW, Q4 2026
Project value
$14.5B
Status
Under construction
Sector
AI and data centers

Overview

1.2 GW Behind the Meter

San Marcos Data Center I is a 1.2 GW AI campus on the I-35 South Data Center Corridor, between Austin and San Antonio, powered entirely by natural gas on site. CloudBurst Data Centers, a Denver developer founded in 2022, and its design-build partner Evolve Holdings, both led by Tye A. Johnson, broke ground in November 2025 and target the first 50 MW for the fourth quarter of 2026.

Unlike the powered-land parks nearby, where a developer leases pads to others, CloudBurst and Evolve develop and build the campus themselves: up to 1.2 GW in three 400 MW phases and 10 to 12 buildings. The 706-acre campus is valued at $14.5B.

Campus profile
DevelopersCloudBurst Data Centers and Evolve Holdings, under Tye A. Johnson
Location2955 Francis Harris Lane, Guadalupe County, on the Hays County line between San Marcos and New Braunfels
CapacityUp to 1.2 GW in three 400 MW phases; 10 to 12 buildings
PowerOn-site natural gas; no grid connection needed
Gas supplyEnergy Transfer Oasis pipeline, 10-year deal, up to 450,000 MMBtu a day, more than 1.8 GW of generation potential
CoolingClosed-loop water; test beds for liquid and hybrid cooling
Project value$14.5B
Land706-acre campus
County approvalGuadalupe County Commissioners Court, 3-2, April 21, 2026
StatusUnder construction since November 2025; first 50 MW targeted Q4 2026

Behind the meter

More Gas Than the Campus Needs

CloudBurst signed a 10-year agreement with Energy Transfer, the Dallas pipeline company, for up to 450,000 MMBtu a day of firm gas through the Oasis pipeline, enough for more than 1.8 GW of generation against 1.2 GW of planned load. The headroom covers redundancy and backup across the phases and keeps the campus off the ERCOT interconnection queue and transmission build-out that gate grid-connected projects.

That puts it with the other gas-powered Texas campuses, Sandow Lakes, Fermi America and the Permian sites, with an unusually high ratio of gas supply to load. The cost is emissions and air quality over the life of the plant, and a gas plant needs a TCEQ air permit, which the state's September 2026 pause on data center permits now holds up for new applications; see Behind-the-Meter Power.

The county

Approved by Guadalupe County

The campus lies outside the city limits and extraterritorial jurisdiction of both San Marcos and New Braunfels, so the county decides. Guadalupe County Commissioners Court approved the development agreement and tax abatement 3-2 on April 21, 2026, against a minimum investment of $500M. The agreement runs with the land and is void if the property is ever used for housing.

County approval is becoming the common route on the corridor: Tract Caldwell Valley's PowerHouse pad was de-annexed from Uhland into Caldwell County, and Project Mustang threatened to build in Williamson County before Taylor annexed it on the city's terms.

The corridor

Neighbors on I-35 South

Sabey Data Centers is planning a 786-acre campus nearby; San Marcos council opened development-agreement talks in June 2025. Sabey's Round Rock campus hosts TACC's Horizon supercomputer. To the north toward Uhland, Tract Caldwell Valley, Prime and Edged extend the corridor. Cushman & Wakefield counted 7,823 MW planned, 615 MW under construction and 1,154 MW operating in the Austin and San Antonio markets at the end of March 2026.

Record

Dataset Record

Dataset
Texas data centers (texas_data_centers): CloudBurst San Marcos Data Center
Sources
CloudBurst, Energy Transfer, Guadalupe County Commissioners Court, Cushman & Wakefield, local reporting
Capacity
The 1.8 GW is gas-supply generation potential, not IT load
Last verified
Q4 2026