Overview
Up to 1 GW on Its Own Gas
Project Mustang, now called the Taylor Technology Campus, is a data center campus on 664 acres of former farmland at 3301 FM 112, between FM 112 and US 79 at the eastern edge of Taylor. Big Watt Digital of South Dakota and PowerHouse Data Centers of Virginia, through PH Digital, plan up to 1 GW of data center load on a 750 MW natural gas plant on site, with a 500 MW first phase and first power targeted for the first half of 2028.
It is the fourth Taylor-area data center on the US 79 corridor and the only one that brings its own generation. PowerHouse is also the pad operator inside Tract Caldwell Valley on the I-35 South corridor.
| Developers | Big Watt Digital (South Dakota) and PowerHouse Data Centers through PH Digital (Virginia) |
|---|---|
| Location | 3301 FM 112, east of Taylor, Williamson County |
| Land | 664 acres of former farmland |
| Capacity | Up to 1 GW of data center load; 500 MW first phase |
| Power | 750 MW on-site natural gas plant, behind the meter |
| Cooling | Closed-loop, on non-potable water, required by the city agreement |
| Community commitment | $28.2M |
| City agreement | 20-year annexation and development agreement, approved 5-0 on October 8, 2026 |
| First power | First half of 2028 (target) |
The annexation fight
From Walkout to Agreement
The site is in Taylor's extraterritorial jurisdiction, outside city limits, where the city says it has no authority to regulate a project. The developers asked to be annexed, which would let Taylor set binding rules on noise, setbacks, air quality, water and stormwater. After a packed August 2026 hearing, the Planning and Zoning Commission voted 6-2 to table the zoning for 90 days while it wrote data center guidelines.
In early September the developers withdrew the annexation request and said they would build in unincorporated Williamson County instead. The city came back to the table: on October 8 the council voted 5-0 for a 20-year annexation and development agreement that requires closed-loop cooling on non-potable water, with $28.2M in developer commitments to the community. The city projects $1.38B in tax revenue over the 20 years.
The state pause
The Gas Plant Needs a State Permit
Annexation settles the city's role, not the state's. On September 21, 2026 Governor Abbott ordered TCEQ to pause air and water permits for data centers and the power plants that serve them until ERCOT finishes its review of large loads, expected in December. The 750 MW gas plant needs an air permit, so Mustang is the US 79 campus most exposed to the pause. Public Citizen and FracTracker reported on October 19 that TCEQ has kept processing some data center permits; see Texas Data Center Moratorium and Behind-the-Meter Power.