I-35 South Data Center Corridor

Supernode · San Marcos, Uhland and Maxwell · Hays, Caldwell and Guadalupe counties

The supercluster's southward extension toward San Antonio: multi-gigawatt campuses on farm land with grid, gas and fiber in reach. Nothing is running yet, and Tract Caldwell Valley alone is planned for 4 GW.

  • Under construction
  • Planned or pre-construction
  • Contested
  • Gas pipeline
  • Gas peaker
Map of the I-35 South corridor between Austin and San Antonio: data center campuses in Hays, Caldwell and Guadalupe counties sized by planned capacity, with the gas pipelines and the LCRA Timmerman peaker LCRA Timmerman peaker, 380 MW gas, online 2024 Tract Caldwell Valley: 4,000 MW planned, planned or pre-construction CloudBurst Evolve San Marcos: 1,200 MW planned, under construction PowerHouse (pad inside Tract): 700 MW planned, contested Edged Energy Maxwell: capacity not disclosed, under construction Prime Project Snow: capacity not disclosed, planned or pre-construction Sabey San Marcos: capacity not disclosed, planned or pre-construction BUDA KYLE SAN MARCOS NEW BRAUNFELS LOCKHART UHLAND MAXWELL SEGUIN LULING TRACT CALDWELL VALLEY CLOUDBURST TIMMERMAN AUSTIN SAN ANTONIO I-35 SH 130 OASIS GAS PERMIAN HIGHWAY GAS HAYS CALDWELL GUADALUPE COMAL LOCATIONS APPROXIMATE; PIPELINES SCHEMATIC
Planned capacity
5,200 MW+
Land held
5,028 acres
Disclosed capital
$26B+
Operating today
0 MW
First power
Q4 2026
Sector
AI and data centers

Overview

Between Austin and San Antonio

Compare the campuses by capacity, land or disclosed capital.

The I-35 South Data Center Corridor runs through Hays, Caldwell and Guadalupe counties between Austin and San Antonio, which have their own pages. It is the southward supernode of the Austin Supercluster and the youngest: no campus is operating yet. CloudBurst's first 50 MW, due late 2026, would be the corridor's first live power.

Five developers hold about 5,000 acres with 5,200 MW of disclosed planned capacity, most of it in unincorporated Caldwell County around Uhland and Maxwell. PowerHouse leases a 500-acre pad inside Tract. Tract, Edged and Prime sit within six miles of the FM 2720 and SH 142 intersection, on land that had no data centers before 2024.

Compare

Tract Caldwell ValleyTract Caldwell Valley Sabey San MarcosSabey San Marcos CloudBurst Evolve San MarcosCloudBurst Evolve San Marcos PowerHouse (pad inside Tract)PowerHouse (pad inside Tract) Edged Energy MaxwellEdged Energy Maxwell Prime Project SnowPrime Project Snow

Under construction   Planned or pre-construction   Contested   A blank bar is a figure the developer has not disclosed.

All campuses as a table
Data center campuses on the corridor
CampusCountyPlannedAcresCapitalPowerDeveloperStatus
Tract Caldwell ValleyCaldwell4,000 MW3,000-Grid and on-site gasTract (powered land; operators lease pads)Site prep under way; Bluebonnet and LCRA substation scaling to 1.6 GW; no tax abatement requested
Sabey San MarcosHays-786-GridSabey Data CentersCity council negotiation opened June 2025
CloudBurst Evolve San MarcosHays / Guadalupe1,200 MW706$14.5BOn-site gasCloudBurst and Evolve HoldingsBroke ground November 2025; Energy Transfer Oasis gas for more than 1.8 GW of generation
PowerHouse (pad inside Tract)Caldwell700 MW500-Grid and on-site gasPowerHouse Data Centers (AREP)A 500-acre pad inside Tract Caldwell Valley, not added to the totals; de-annexed from Uhland April 2026
Edged Energy MaxwellCaldwell-330$7.3BGridEdged (Endeavour)Beside the LCRA Timmerman 380 MW peaker; waterless ThermalWorks cooling; Phase 1 building from June 2026
Prime Project SnowCaldwell-206$4.2BGridPrime Data CentersNine buildings in three phases; Caldwell County abatement and TIRZ approved March 2024

Tract Caldwell Valley

The Corridor's Largest Site

Featured campus

Tract Caldwell Valley Technology Park

Land
2,973 contiguous acres near Uhland
Planned
Up to 4 GW
First phase
360 MW, 250 MW contracted, Q1 2028
Power
Bluebonnet and LCRA substation to 1.6 GW; Kinder Morgan Permian Highway gas
Model
Powered land: Tract entitles and powers pads, operators lease and build
Incentives
No tax abatement requested

Full Tract Caldwell Valley profile

Tract does not run data centers. It buys large parcels, wins zoning, power and fiber, and leases shovel-ready pads to operators who build their own halls. It closed 1,515 acres from Walton Global Holdings in May 2025 and added 1,458 more in January 2026, lifting the master plan to 4 GW, about four times the whole Cedar Creek cluster.

First power

Zero Megawatts Today

2027 2028 2029 TODAY CloudBurst Evolve San Marcos: Q4 2026, 50 MWCloudBurst Evolve San Marcos Q4 2026, 50 MW Tract Caldwell Valley: Q1 2028, 250 MWTract Caldwell Valley Q1 2028, 250 MW Edged Energy Maxwell: June 2028, Phase 1Edged Energy Maxwell June 2028, Phase 1 PowerHouse (pad inside Tract): Not announcedPowerHouse (pad inside Tract) Not announced Prime Project Snow: Not announcedPrime Project Snow Not announced Sabey San Marcos: Not announcedSabey San Marcos Not announced

CloudBurst comes first because it does not wait for the grid: Energy Transfer's Oasis pipeline can supply more than 1.8 GW of on-site generation, more than the campus plans to use. Tract and Edged connect through Bluebonnet and LCRA substations and arrive in 2028.

Why here

Four Constraints Solved, One Open

Why the corridor works, and where it does not
PowerThree paths: the grid through Bluebonnet and LCRA, Energy Transfer's Oasis pipeline and Kinder Morgan's Permian Highway pipeline for on-site gas, and the LCRA Timmerman peaker at Maxwell
LandFormer farm parcels in the hundreds to thousands of acres at rural prices; Tract alone holds about 3,000
PermittingUnincorporated Caldwell County approves the largest campuses through the commissioners court, with no city zoning layer
FiberLong-haul routes along I-35 between the Austin and San Antonio interconnection points
WaterNot solved: Edwards Aquifer drought rules and local opposition; San Marcos denied a project inside city limits in February 2026

Edged's waterless cooling and the on-site gas plants with dry cooling are the corridor's answers to water. Evaporative cooling at gigawatt scale is still the limit that permitting speed cannot get around.

In the supercluster

Two Data Center Vectors South and East

I-35 South holds more planned capacity, land and developers than the Cedar Creek cluster, but Cedar Creek has a building nearing completion while I-35 South's first megawatt is still months away. They draw on different gas pipelines, substations and county governments, and both serve a buildout whose manufacturing core sits at Giga Texas and Samsung Taylor.

Record

Dataset Record

Dataset
Texas data centers (texas_data_centers) for Tract, CloudBurst, PowerHouse and Sabey; developer-stated figures for Edged and Prime
Extent
Hays, Caldwell and Guadalupe counties; Austin and San Antonio excluded
Capacity
Planned full buildout as disclosed; Edged, Prime and Sabey have not disclosed megawatts
Map
Locations approximate; pipelines schematic
Last verified
Q4 2026