Brownfield Inheritance

Retired industrial sites · Milam, Grimes, Angelina, Dickens · Texas

Texas AI campuses and fabs keep landing on sites built for an earlier industry, inheriting the zoning, rail, water and grid connections already in place. Riot's Rockdale site on the former Alcoa smelter tract now leases AI capacity to AMD on a 700 MW grid connection built for aluminum.

SANDOW LAKES (MILAM, LEE) 31,000 acres, ex-Alcoa RIOT ROCKDALE 700 MW grid connection GIBBONS CREEK (GRIMES) Coal-plant cooling reservoir AMP Z LUFKIN (ANGELINA) 55 MW paper-mill tie GALAXY HELIOS (DICKENS) 1.6 GW ERCOT-approved
Largest tract
31,000 acres
Prior uses
Smelting, coal, paper
Key asset
Water and grid ties
Crypto sites
Converting to AI
Counties
Milam, Grimes, more
Sector
Energy

Overview

Old Industrial Sites Arrive With Water, Rail and Grid Ties Already Permitted

A retired smelter, coal plant or paper mill leaves behind heavy-industrial zoning, rail spurs, road access, a grid interconnection and often water rights or a cooling reservoir. A new tenant on that land skips years of greenfield permitting and queue time.

In ERCOT (the Electric Reliability Council of Texas), where large-load requests reached about 474.7 GW by June 2026, an existing interconnection is the scarcest asset on any site.

Profile
PatternAI and fabs reuse retired industrial sites
Inherited assetsZoning, rail, grid ties, water
Largest tractSandow Lakes, about 31,000 acres
Water caseGibbons Creek Reservoir, Grimes County
Grid caseRiot Rockdale, 700 MW
Crypto-to-AI caseGalaxy Helios, Dickens County
Grid operatorERCOT
Related lawSB 6 (2025) large-load rules
Principal Texas inheritances
SitePrior industryInherited platformCurrent use
Sandow Lakes (Milam, Lee)Alcoa smelter and lignite power, 1950s to 2010sAbout 31,000 acres, rail, cooling lakes, grid tiesRiot and Bitdeer data and mining sites, T1 solar cells, planned 1,200 MW gas plant
Gibbons Creek (Grimes)Coal plant and lignite mineCooling reservoir and generation-era interconnectionSpaceX Terafab production fab
Giga Texas (Travis)Sand and gravel quarryAbout 2,100 acres near SH 130 and the Colorado RiverVehicles, Cortex compute, Terafab research fab
Amp Z Lufkin (Angelina)Southland Paper newsprint millAbout 1,041 acres, rail, 55 MW interconnectionProject Lufkin data center campus
Permian BasinOil and gas productionGas pipelines, produced-water handling, workforceBTM gas campuses such as GW Ranch

Sandow Lakes

The Former Alcoa Smelter Now Hosts Data Centers, Solar Cells and a Gas Plant

Alcoa's Rockdale smelter in Milam County was sited for local lignite and closed after US power prices made aluminum uneconomic. Xebec bought about 31,000 acres across Milam and Lee counties from Alcoa in 2021 for $240M, and Sandow Lakes Energy plans a 1,200 MW gas plant with Siemens turbines on part of the property, targeting 2028.

T1 Energy's G2_Austin solar cell factory in Rockdale is an $850M, 5 GW-a-year plant. Bitdeer runs a large Bitcoin mine at Rockdale. Riot Platforms bought 200 acres under its Rockdale site for $96M in January 2026 and signed its first data center lease with AMD: 25 MW of IT load, with options that could take AMD to 200 MW. Riot plans to convert the site's full 700 MW grid connection to data center use.

Gibbons Creek and Lufkin

A Coal Reservoir Supplies Terafab and a Paper Mill Tie Seeds Project Lufkin

SpaceX and Governor Abbott confirmed Terafab at the retired Gibbons Creek coal plant in Grimes County on Aug 6, 2026: a first phase of more than $16.8B and about 3,000 jobs, backed by a $30M Texas Enterprise Fund grant. SpaceX plans to draw industrial water from Gibbons Creek Reservoir instead of local groundwater. The Terafab research fab sits at Giga Texas, itself built on a former quarry.

The Southland Paper mill east of Lufkin made newsprint from southern pine from 1940 to 2007. Amp Z plans to grow the mill's 55 MW grid connection to 175 MW in 2026 and 1.1 GW in 2028, then add 1 GW of self-generation in 2029 for a 2.1 GW campus on about 1,041 acres.

Crypto to AI

Bitcoin Mines Built the Substations AI Campuses Now Use

Miners drawn to Texas wind and fast interconnection built substations, transmission ties and high-density cooling from 2018 onward. As AI demand crossed the gigawatt scale, those sites became data center campuses.

Texas crypto-to-AI conversions
SiteMining originConversionStatus
Galaxy Helios (Dickens County)Argo Blockchain site, bought by Galaxy for about $65M in 2022CoreWeave lease, 800 MW; 1.6 GW ERCOT-approved, up to 3.5 GW potentialFirst 133 MW phase due 2026, rest through 2027
Riot Rockdale (Milam County)Bitcoin mine on the former Alcoa tractAMD lease, 25 MW with options to 200 MWDelivering in 2026
Core Scientific DentonBitcoin mine, converted under 2024 city amendmentsGPU colocation for CoreWeaveOperating
Soluna Project KatiWind-linked flexible-load site166 MW Bitcoin and AI/HPCKati 1 complete
Coleto Creek (Goliad County)Vistra coal plant retiring 2027Repowering with up to 600 MW of gasNo data center tenant announced

Untenanted Sites

Northeast Texas and the Panhandle Hold Retired Coal Sites Without AI Tenants

Northeast Texas holds the largest unclaimed coal-plant sites in the state: Big Brown in Freestone County (1,150 MW, retired 2018), Monticello in Titus County (retired 2018) and Pirkey near Hallsville (retired 2023). None has an announced AI tenant.

In the Panhandle, Xcel Energy converted the 1,018 MW Harrington Station in Potter County from coal to gas in 2025, keeping its interconnection in place. Tolk Station in Lamb County is scheduled to retire in 2032. Both sit near the Panhandle wind belt where Galaxy Helios operates.