Crusoe Abilene (Campus 2)

Crusoe · Abilene · Taylor County

Crusoe develops, owns and operates a 900 MW campus in Abilene and leases it to Microsoft, next to the Stargate site Crusoe built for Oracle and OpenAI. Microsoft signed for the capacity after Oracle and OpenAI dropped their plan to expand Stargate Abilene in March 2026.

Who holds each layer of the Crusoe Abilene Campus 2 deal: Crusoe holds site, power and operations; Microsoft is the tenant. WHO HOLDS EACH LAYER LAND AND SITE Crusoe, parcel beside Stargate Abilene POWER Crusoe on-site plant + MV battery BUILDINGS AND OPERATIONS Crusoe develops, owns and operates COMPUTE Next-generation GPUs, vendor not named TENANT Microsoft
Planned
900 MW
Power
On-site plant + battery
Buildings
Two at 336 MW IT
Status
Under construction
County
Taylor
Sector
AI and data centers

Overview

Crusoe Builds and Runs a 900 MW Campus for Microsoft

Crusoe announced the campus on March 27, 2026, with Microsoft as the named customer. Two buildings are each designed for 336 MW of critical IT load, fed by a dedicated 900 MW behind-the-meter (BTM) power plant paired with a medium-voltage (MV) battery energy storage system (BESS). Land clearing started at announcement, and the first building is due to energize in mid-2027.

With the adjacent Stargate Abilene campus at about 1.2 GW, Crusoe puts its combined Abilene footprint at about 2.1 GW. Cooling is Crusoe's closed-loop, non-evaporative liquid system, the same design used at Stargate.

Profile
Developer, owner, operatorCrusoe
TenantMicrosoft
LocationAbilene, Taylor County, beside Stargate Abilene
IT capacity900 MW; two buildings at 336 MW critical IT each
PowerDedicated 900 MW on-site plant with MV battery storage
CoolingClosed-loop, non-evaporative liquid cooling
AnnouncedMarch 27, 2026
First buildingEnergized mid-2027 (target)
StatusUnder construction

Deal structure

Microsoft Took the Capacity Oracle and OpenAI Passed Up

Oracle and OpenAI had planned to grow Stargate Abilene from about 1.2 GW toward 2 GW. On March 6, 2026, Bloomberg reported that they had dropped the expansion over financing strain and shifting OpenAI demand forecasts; OpenAI said it would place the capacity at other sites. Nvidia reportedly paid Crusoe a $150M deposit to hold the freed space for its hardware. Three weeks later Crusoe named Microsoft as the tenant for a new 900 MW build next door.

The two campuses share a developer and a town but not a deal. Microsoft's lease is a standalone contract with Crusoe and sits outside the Stargate joint venture of OpenAI, Oracle, SoftBank and MGX. See Microsoft's Texas compute and OpenAI's Texas compute.

The two Abilene campuses
Campus 1: Stargate AbileneCampus 2: Microsoft
CapacityAbout 1.2 GW, eight buildings900 MW, two buildings
DeveloperCrusoeCrusoe (also owner and operator)
Compute operatorOracle Cloud InfrastructureCrusoe
TenantOpenAIMicrosoft
ProgramStargate joint ventureStandalone lease
StatusTwo buildings live; six more due by end of 2026Under construction; first building mid-2027

Energy model

A Dedicated Plant Sized to the Campus

Crusoe calls itself an AI factory company: it builds the power plant, the buildings and the cooling as one product and leases the result. At Campus 2 the on-site plant matches the 900 MW campus load, with the MV battery system covering fast load swings and reliability. Crusoe has not said how much of the load will draw on the Electric Reliability Council of Texas (ERCOT) grid, if any.

Liquid cooling delivered direct to the racks is what makes 336 MW per building workable, and the closed loop keeps on-site water use far below an evaporative design. See Behind-the-Meter Power and Water and Cooling.

Constraints

Abilene Power Permits Sit at TCEQ

Crusoe's existing Longhorn Data Center Power Plant at the Stargate site runs 10 gas turbines and 62 diesel generators under minor permits issued in 2024. A major air permit application to add 41 turbines is pending at the Texas Commission on Environmental Quality (TCEQ), which granted a public meeting in September 2026 at the request of State Rep. Stan Lambert. Public filings do not tie that expansion to the Microsoft campus, but any major air permit for Abilene generation falls under Governor Abbott's September 21, 2026 pause on data center permits, expected to hold until ERCOT's large-load review finishes in mid-December. See the Texas data center permit pause.

Record

Dataset Record

Sources
Crusoe newsroom, Data Center Dynamics, Bloomberg, Data Center Knowledge, Texas Tribune / Floodlight, Abilene Reporter-News, Office of the Governor of Texas
Last verified
October 2026