Meta El Paso

Meta · El Paso, El Paso County

Meta is the primary tenant at Meta El Paso in El Paso, El Paso County. AI Training + Inference for Muse runs here.

  • On-site gas
  • Co-located renewables
  • Nuclear
  • Grid
Capacity
1,000 MW
Status
Under Construction
Power source
On-site gas
Chips
Nvidia GPUs / Meta MTIA
Operational
2028

Profile

Meta at Meta El Paso

Dataset profile
TenantMeta
FacilityMeta El Paso
OperatorMeta / BlackRock (GIP) joint venture
LocationEl Paso, El Paso County
Capacity (MW)1,000
StatusUnder Construction
TypeAI Factory
WorkloadAI Training + Inference
ProductMuse
PowerEl Paso Electric grid plus 813 modular gas generators (366 MW)
ChipsNvidia GPUs / Meta MTIA
Operational2028
Investment ($B)10

Notes

Site Notes

Ground broken Oct 2025 at $1.5B and 1.2M sq ft; raised to $10B and 1 GW on 26 Mar 2026. A BlackRock strategic venture now develops the campus with Meta as construction manager and initial sole occupant. Meta has contracted 5,000+ MW of clean power to the Texas grid.

Other sites

Other Meta Sites in Texas

2 other Meta sites in the dataset
FacilityLocationStatusCapacity (MW)
Meta Fort WorthFort Worth, Tarrant CountyOperational (expanding)-
Meta TempleTemple, Bell CountyUnder Construction198

Record

Dataset Record

Dataset
Frontier lab and hyperscaler data centers in Texas (llm_data_centers2026), row AI010