Profile
Meta at Meta El Paso
| Tenant | Meta |
|---|---|
| Facility | Meta El Paso |
| Operator | Meta / BlackRock (GIP) joint venture |
| Location | El Paso, El Paso County |
| Capacity (MW) | 1,000 |
| Status | Under Construction |
| Type | AI Factory |
| Workload | AI Training + Inference |
| Product | Muse |
| Power | El Paso Electric grid plus 813 modular gas generators (366 MW) |
| Chips | Nvidia GPUs / Meta MTIA |
| Operational | 2028 |
| Investment ($B) | 10 |
Notes
Site Notes
Ground broken Oct 2025 at $1.5B and 1.2M sq ft; raised to $10B and 1 GW on 26 Mar 2026. A BlackRock strategic venture now develops the campus with Meta as construction manager and initial sole occupant. Meta has contracted 5,000+ MW of clean power to the Texas grid.
Other sites
Other Meta Sites in Texas
| Facility | Location | Status | Capacity (MW) |
|---|---|---|---|
| Meta Fort Worth | Fort Worth, Tarrant County | Operational (expanding) | - |
| Meta Temple | Temple, Bell County | Under Construction | 198 |
Record
Dataset Record
- Dataset
- Frontier lab and hyperscaler data centers in Texas (llm_data_centers2026), row AI010
- Fields
- Shown as stored; the company page carries the reviewed narrative