AWS at AWS GW Ranch
| Tenant | AWS |
|---|---|
| Facility | AWS GW Ranch |
| Operator | Amazon AWS / Pacifico Energy (power developer) |
| Location | Pecos County |
| Capacity (MW) | 7,650 |
| Status | Under Construction |
| Type | AI Factory |
| Workload | AI + Cloud |
| Product | Nova + AWS |
| Power | Off-grid behind-the-meter: 35 gas turbines up to 7.65 GW, plus 750 MW solar and 1.8 GW battery |
| Chips | Trainium / Nvidia |
| Operational | Dec 2026 first buildings |
| Investment ($B) | - |
The capacity figure is the generation capacity of the on-site plant, not IT load.
Notes
Site Notes
8,000-acre campus acquired from Pacifico Energy; Amazon confirmed ownership Aug 2026. Three 189,000 sq ft buildings permitted at about $300M each. AWS's first major behind-the-meter off-grid commitment. Permitted emissions upward of 30M metric tons CO2 per year. The 7.65 GW is generation capacity, not IT load.
Other sites
Other AWS Sites in Texas
| Facility | Location | Status | Capacity (MW) |
|---|---|---|---|
| AWS Project Eagle | Boling, Wharton County | Under Construction | - |
| AWS Comanche Peak (Project Spectrum) | Glen Rose, Somervell County | Filed / Planned | 1,200 |
| AWS Cedar Creek | Cedar Creek, Bastrop County | Land Secured | - |
| AWS Round Rock | Round Rock, Williamson County | Zoned / Planned | - |
| AWS San Antonio (Rockfish, Bitter Blue) | San Antonio, Bexar County | Operational / Under Construction | - |
| AWS Floydada | Floydada, Floyd County | Filed / Planned | - |
Record